Pipeline Construction 

High pressure gas pipeline STEG (Tunis – Beja)

Gas Pipeline Construction from Mornaguia to Mjez Elbeb and from Mjez Elbeb to Béja

Length: 57 km, 20Inch

              16 km, 24Inch

Civil and pipeline construction works including 2 pig stations (launchers & receivers), block valve stations, FOC installation, Scada system installation.

High pressure gas pipeline OMV / ETAP (CPF Nawara – GTP Gabes) 

Gas Pipeline construction for the interconnection of Nawara CPF to the GTP Gabes.

Length: 370 km, 24Inch

Engineering, Procurement, Construction, testing, commissioning and Start-up including pig stations, valve stations, control & telecommunications systems, fiber optic cable and crossings.

High pressure gas pipeline STEG (Feriana – Gafsa)

Gas Pipeline Construction for the interconnection of Coal mines in Gafsa valley.

Length: 95 km, 20Inch

               75 km, 8Inch

Engineering, Procurement, Construction, testing, commissioning and Start-up including valve stations and crossings.

High pressure gas pipeline STEG (Gabes – Zarzis)

Gas Pipeline Construction from Gabés to Zarzi

Length: 155 km, 12Inch

Civil and pipeline construction works including 2 pig stations (launchers & receivers), 5 block valve stations and Facility & metering system.

Condensate pipeline BG Tunisia (Sfax – Skhira)

Condensate Pipeline Construction from Hannibal Gas Plant to TRAPSA Terminal.

Length: 60 km, 8Inch

Engineering, Procurement, Construction, testing, commissioning including 2 pig stations (launchers & receivers), 33 block valve stations, Facility & metering system.

LPG pipeline BG Tunisia (Sfax – Gabes)

Construction of Two parallel LPG Pipelines from Hasdrubal Plant to GABES Terminal.

Length: 260 Km, 6Inch (130 km x 2)

Engineering, Construction, testing and commissioning including special crossings.

Multiphase and Gas Pipelines BG Tunisia (Hannibal GP – Ben Sahloun)

Gas pipeline construction From Hannibal Gas plant to Ben Sahloul.

Length: 20 Km, 18Inch

Engineering, Construction, testing and commissioning

Flowline construction ENI (Oued Zar – Trapsa)

Flowline Construction for the interconnection of CPF Oued Zar and pipeline 24” Trapsa.

Length: 10 km, 12Inch

Engineering, Construction, testing and commissioning

Pipeline construction ENI (Nadir Well – Hawa Manifold)

Pipeline Construction from Nadir Well to Hawa Manifold in Oued Zar.

Length: 17 km, 8Inch

Engineering, Procurement, Construction, testing, commissioning and Start-up including EPC manifold & related piping HP.

Pipeline construction ENI (Djebel Grouz)

Pipeline Construction for the interconnection of CPF Djebel Grouz and STEG pipeline.

Length: 4 km, 6Inch

Engineering, Procurement, Construction, testing, commissioning.