PIPELINE CONSTRUCTION

Project Overview

EPC  project  (In  JV  With  MS  Italy)  Gas  Pipeline construction for the interconnection of Nawara CPF to the GTP Gabes the projet include Western Gas Pipeline from Nawara to Gabès GTP (370 Km 24”)

  • 2 pig stations (launchers & receivers).
  • 12 block valve stations.
  • Control and Telecommunications Systems
  • Fibre-Optic Cable

PROJECT

  • Km 24”

Gas Pipeline Nawara– Gabes

Client

  • OMV

Location

  • Nawara – Gabes
  • Completion DateIn Progress

Project Overview

Gas Pipeline for the interconnection of Coal mines in the Gafsa valley : Engineering, Procurement, Construction, testing, commissioning and Start-up for 95 Km of 20” & 75 Km of 8” Gas Pipeline From Feriana to Gafsa

PROJECT

  • 95 Km 20” 75 Km 8” Gas Pipeline
  • Feriana – Gafsa

Client

  • STEG

Location

  • Coal mines in Gafsa valley

Completion Date

  • 2016

Project  Overview

150 Km of 12” Pipeline from Gabés

to Zarziz

Construction , Testing &

commissioning of 155 Km of 12 »

pipeline from Gabés to Zarzis

including:

  • 2 pig stations (launchers & receivers).
  • 5 block valve stations.
      • 2 pig stations (launchers &receives).33 block valve stations block valve stations.Facility & metering system.PROJECT155 Km 12” Gas Pipeline Gabés – Djerba – Zarzis

        Client

        STEG

        Location

        Gabés – Djerba – Zarzis

        Completion Date

        2016

Project Overview

Engineering, Procurement, Construction , Testing & commissioning of 8 » pipeline from Hannibal Gas Plant – TRAPSA Terminal.

  • 58 Km of 8’’ condensate pipeline and associated works from Hannibal plant (sfax) to Trapsa Terminal(Skhira).
  • 2 pig stations (launchers &receives).
  • 33 block valve stations block valve stations.
  • Facility & metering system.

PROJECT

8” Pipeline from Hannibal Gas Plant TRAPSA terminal

Client

BG TUNISIA

Location

Hannibal Gas Plant-TRAPSA Terminal

Completion Date

2006

Project Overview

  • Hasdrubal Project : 260 Km of 6’’ LPG Pipeline From hanibalGas plant to Gabes
  • 20 Km of 18’’ Multiphase and Gas Pipelines From hanibal Gas plant to Ben Sahloul

PROJECT

  • LPG & Gas
  • Pipeline

Client

  • BG TUNISIA

Location

  • Sfax/Gabes

Completion Date

2009

Project Overview

 

 

vEngineering, procurement  and construction of 4 Km

vPipeline Interconnection from Djebel Grouz to

pipeline 10″ STEG

 

v10 Km of 12″ Flowline Construction From Oued Zar to Trapsa

 

v9 Km of 12″ Pipeline Construction From Oued Zar to Trapsa

PROJECT

  • Gas Pipeline

Client

  • ENI

Location

  • Oued Zar

Completion Date

  • 2008

Project Overview

  • Gas pipeline looping:
  • 10 Km of 20″ diam pipeline and related civil works at El Mourouj.
  • 12 Km of 8″ diam pipeline and related civil works at Jbel El Oust.
  • 5 Km of 4 » diam pipeline and related civil works in Denden city.
  • 4 Km of 12″ diam pipeline and related civil works from La Goulette to Radés, including 500 m of horizontal drilling.
  • 13 Km of 20” diameter , 11.2 mm thick pipe+ fiber optic cable

 5 km of 16 “ diameter , 9.2 mm thick pipe .

PROJECT

Gas pipelines

interconnection

Client

STEG

Location

Tunis &Suburbains

Completion Date

2000-2004

PROJECT

Pipelines Gaz

Completion Date

2006

Project Overview

Designed to transport gas and condensate from two distant fields in the Tunisian desert, this project was completed in six months. . Activities included Survey & right of way, pipe transport & stinting, welding & NDT, coating, lowering-in and backfilling, installation of pig scrapers, block valves hydro-testing, tie-in to existing lines and pre-commissioning.

Two main segments were included in this pipeline:

  • 116 km of 10” FBE coated pipe from El franig wellhead to the CPF.
  • 5 Km of 6” FBE coated pipe from Bagel wellhead to junction point .

PROJECT

  • EL Franig/ Baguel Development-Pipeline project

Client

  • CMS
  • NOMECO

Location

  • Douz
  • ( South Tunisia)

Completion Date

  • 1998

Project Overview

  • 300 Km of 6” pipeline transporting

L.P.G from El Borma production field to the fractionating plant in Gabes .

  • 50 Km of 6” flow lines .
  • The construction of the pipeline included in field coating, pipe laying through rocky mountains and major rivers, special points, installation of pig launchers & receivers and cathodic protection etc.

PROJECT

  • LPG
  • Recovery
  • system

Client

  • STEG

Location

  • El Borma –Gabes

Completion Date

1985