High pressure gas pipeline STEG (Feriana – Gafsa)

Gas Pipeline Construction for the interconnection of Coal mines in Gafsa valley.
Length: 95 km, 20 »

75 km, 8 »
Engineering, Procurement, Construction, testing, commissioning and Start-up including valve stations and crossings.

PROJECT: 95 Km 20” 75 Km 8” Gas Pipeline – Feriana –Gafsa
Project Overview :
Gas Pipeline for the interconnection of Coal mines in the Gafsavalley : Engineering, Procurement, Construction, testing, commissioning and Start-up for 95 Km of 20” & 75 Km of 8” Gas Pipeline From Ferianato Gafsa
Client : STEG
Location : Coal mines in Gafsa valley
Completion Date: 2016