Project Description :
*Construction of an Offshore Drilling Platform for Ashtart :
* Construction and erection of 2000 tons of structure.
* Fabrication and erection of 200 tons of piping.
* Equipment installation and connection including :
* 2 sets of turbo generators of 3MW.
* 2 turbo pumps
* Fuel gas and diesel oil treatment units
* Compressed air and chemical units
* Construction and installation of electrical and control rooms.
* Electrical and instrumentation works.
* Painting and insulation.
* Sea fastening and load out.

Location: Gulf of Gabès TUNISIA
Contract Period: 08 Months
Completion Date: 1986